Ghana
Navrongo

Navrongo Water Treatment plant

Año
  • 2020
País
Ghana
Ciudad
Navrongo
Estado
  • Realizado
Capacidades
Cliente
  • Republic of Ghana
Partners
  • Denys Engineers & Contractors BV
Objetivos de Desarrollo Sostenible
Agua limpia y saneamiento Ciudades y comunidades sostenibles

New water treatment plant aimed at improving water supply in and around Navrongo

The project involved the design and construction of:

  • the treatment plant  (20,500 m³/day),
  • two new elevated water reservoirs (600 m³ and 400 m³),
  • three buildings, including one for the General Services, 
  • a building housing the reception (20x20m),
  • a high-lift pump station with underground reservoir, 
  • a foundation slab for the Chemical Waste Treatment Plant,
  • an intermediate pumping station (70 m³/h),
  • a chemical building. 

 

Nuestra Mision

Structural engineering services:

  • formwork drawings (concrete structures) based on the process plans,
  • reinforcement drawings (reinforced concrete structures),
  • quantity survey related to the formwork drawings (cubi meters of concrete and formwork),
  • steel list,
  • list of plans.