Tabuleiros Litoraneos Irrigation Project – Phase II
- Año
-
- 2021
- País
-
Brasil
- Ciudad
-
State of Piauí
- Estado
-
- Realizado
- Capacidades
- Cliente
-
- DNOCS (National Department of Works Against Drought)
- Objetivos de Desarrollo Sostenible
-
Second phase of an ambitious irrigation project aimed at increasing the surface area of irrigated land to 5,600 hectares
The project concerns the Parnaíba - Buriti dos Lopes area and includes:
- a main pump station with a flow of 6 m³/s (5 pumps of 1,000 hp, with a capacity of 1.2 m³/s each),
- 2 km of two 1.5 diameter pipes conducting water to a reservoir,
- a canal that crosses the irrigated areas and 4 sectorial pump stations,
- a main canal, 15 km long.
Nuestra Mision
- Technical assistance
- Oversight and Inspection